Field Teams OneCrew Required Training Estimated time: 15-20 minutes

Overview

Field employees use OneCrew on company iPads to review scheduled work, understand the Work Order, enter Actuals, upload photos, and communicate job progress or completion to the office.

Accurate and timely field entry helps Operations, Sales, Costing, and other teams understand what happened on the job and what needs to happen next.

The field workflow is not complete until required Actuals are submitted and the job outcome is communicated through the Project Log.

Current iPad Basics Walkthrough

This video demonstrates the current basic iPad workflow, including viewing the schedule, opening the assigned Project or service, reviewing job details, using the Project Log, and uploading photos.

Open Video

Daily Post-Job Workflow: Entering Actuals

This detailed walkthrough demonstrates entering Actuals on the iPad, including labor, materials, equipment, subcontracting, photos, and submission.

The written instructions below include updated completion and communication requirements that may be more specific than the video.

Open Video

OneCrew on Company iPads

The OneCrew mobile app should already be installed on company iPads used by field employees. Employees should not need to install the app themselves.

If the app is missing, will not open, or is not working correctly, contact the IT team for assistance.

Open Your Assigned Work

1

Open OneCrew

Open the OneCrew app on the company iPad.

2

Review the Schedule

The app defaults to the current day. Change the date when needed.

3

Select the Assigned Work

Open the scheduled Project or the specific service assigned to your crew.

4

Get Directions

Use Get Directions when navigation to the job site is needed.

Review the Project and Work Order

Opening the Project shows overall job information. Opening the specific service shows Work Order details related to the work assigned to your crew.

Before beginning work, review all available information, including:

  • Work Order notes and service descriptions
  • Project and service details
  • Maps, photos, and supporting documents
  • Customer or site instructions
  • Checklist items that apply to the work

Do not guess when instructions are missing or unclear. Contact the office before proceeding when the Work Order or site conditions do not match the expected scope.

Pre-Job Actions — Process Confirmation Required

Complete all pre-job actions required by your business unit before beginning work. This section will be expanded after the standard pre-job process is confirmed.

Use the Project Log

The Project Log is the primary way field employees communicate with the office through OneCrew. Use the Log to share important updates and mention specific people.

The Log may be used to communicate:

  • Progress updates
  • Delays or changing site conditions
  • Additional days needed
  • Submitted Actuals
  • Completed work
  • Work that could not be completed

Upload Job Photos

Take relevant photos before, during, and after the job as required by your business unit or the Project instructions.

  • Use the regular iPad Camera app when possible.
  • Upload photos into OneCrew using the camera icon.
  • Keeping the original photos on the iPad helps prevent losing them if an upload fails.
  • Add useful notes when a photo documents an issue, changed condition, or incomplete work.

Enter Actuals

Actuals must reflect what was truly worked or used in the field. Do not simply copy the Estimate without verifying the real job activity.

Start the Entry

  1. Open the scheduled Project or service.
  2. Open the Actuals tab.
  3. Confirm or adjust the work date.
  4. Confirm the correct crew.
  5. Select the service being worked on.
  6. Add notes when needed.

Labor

  • Enter actual hours for the individual employees.
  • Include applicable travel or mobilization time.
  • When one crew works multiple jobs in one day, assign travel time to the appropriate Actuals entry.
  • Leave separate estimate-calculation fields blank when instructed by the current process.

Materials

  • Record the actual quantity of each material used.
  • Use Add Cost when an additional material is not already listed.
  • Explain unusual or unexpected purchases in Notes.

Equipment

  • Record the total time equipment was committed to the job.
  • Use the time the equipment was unavailable for other work, not only active runtime.
  • Add missing equipment when necessary.

Subcontracting and Other Fields

  • Enter subcontractor costs when applicable.
  • Complete additional fields when they appear.
  • Some fields vary by business unit.

Review and Submit Actuals

1

Review the Summary

Confirm all entries are accurate and reflect what actually happened.

2

Correct Errors

Make needed changes before submitting.

3

Check Connectivity

When service is weak, refresh the app before entering or submitting Actuals.

4

Submit

Tap Submit and confirm that OneCrew displays a successful-submission notification.

Before reporting the entire Project complete, confirm Actuals were submitted for every applicable service and every day worked.

Business-Unit Project Checklist

Some business units require a Project checklist. Complete the checklist as directed by your business unit before finishing the job workflow.

Report the Job Outcome

When the Work Is Complete

  1. Confirm all required Actuals have been submitted.
  2. Open the Project Log.
  3. Mention the Operations contact.
  4. Mention the Salesperson responsible for the Project.
  5. Confirm that the work is complete.

When the Work Cannot Be Completed

  1. Open the Project Log.
  2. Mention both the Operations contact and the responsible Salesperson.
  3. Clearly state that the work was not completed.
  4. Explain why it could not be completed.
  5. Describe any relevant issue.
  6. Identify any known follow-up or next step.

When the work is complete, mention both the Operations contact and the Salesperson responsible for the Project in the Project Log to confirm completion. If the job cannot be completed, mention both people and clearly explain why the work could not be completed and any next step that may be required.

For a multi-day Project, only report the Project as fully complete after Actuals have been submitted for every applicable service and day.

Troubleshooting

Issue What to Do
OneCrew app is missing or not working Contact the IT team.
Assigned work is missing Confirm the selected date, then contact the office.
Actuals tab is missing Confirm that the specific Project or service has been opened.
Actuals will not submit Check connectivity, refresh the app, and try again.
Photo upload fails Keep the original photo on the iPad and retry when connectivity improves.
Unsure about a field or checklist Contact the Operations team before submitting.

Final Field Checklist

  • Reviewed the assigned Project and Work Order
  • Completed applicable pre-job requirements
  • Completed the assigned work
  • Entered accurate labor, material, equipment, and other Actuals
  • Uploaded required photos
  • Completed the business-unit checklist when applicable
  • Reviewed and submitted Actuals
  • Confirmed successful submission
  • Mentioned both Operations and Sales in the Project Log
  • Reported whether the job was completed
  • Explained incomplete work and any required next step